Client data · JSW ISPL Raipur: The breakdown sheets the four plants sent, and escalations raised from them, not the live breakdown log (Preview mode: figures computed from client files.).Demo data: Figures the client's files do not carry are filled with representative demo values, the same on every visit, so the screen reads complete. They are not the plant's records.
Logged, escalated, owned, worked, closed. Each step links to the next.
A failure of 60 min or more raises a CAPA by itself
Due 7 days after the breakdown
Reminder 3 days before, then it climbs when overdue
Reminders 3
Overdue59 days past target · remind M.R. KASHYAP, AGM and Head of plant
Overdue55 days past target · remind Vidyadhar, Sr.Engg and Head of plant
Overdue40 days past target · remind Kishun saw, AM and Head of plant
Shown here only: no e-mail or SMS is sent in this demo.
13 of 13 CAPAs · 5 not yet closed
CAPAs
S.No
CAPA no.
Raised
Plant
Equipment
Problem
Owner
Target
Status
Breakdown
Action
1
CAPA-SEI-EI-BD-0002
05 Sep 2026
SMS-II E&I
F/C 1A
F/C 1A: 65 min. trip in GLD
M.r. Kashyap, Agm
12 Sep 2026
OpenAuto draft: to complete59 d past target
ei-BD-0002
2
CAPA-SEI-EI-BD-0011
09 Sep 2026
SMS-II E&I
F/C 3B
F/C 3B: water leakage
Vidyadhar, Sr.Engg
16 Sep 2026
OpenAuto draft: to complete55 d past target
ei-BD-0011
3
CAPA-SEI-EI-BD-0034
24 Sep 2026
SMS-II E&I
F/C 5A
F/C 5A: DUE TO INVERTER DIFFERENTIAL CURRENT
Kishun saw, AM
01 Oct 2026
OpenAuto draft: to complete40 d past target
ei-BD-0034
4
MSL/SID/MECH/K-02/22
28 Sep 2026
Sponge DRI
–
KILN -02 KILN GIRTH GEAR SPRING PLATE No-03 FORK DOWNHILL CRACK. / TOTAL DELAY DURATION=15:43-16:06=23 MINUTE
Amit Singh
29 Sep 2026
Closed
bd-09-K2-2026-09-28
5
MSL/SID/MECH/K-02/21
22 Sep 2026
Sponge DRI
–
Stack cap hose pipe (Kiln side) damaged. / Delay time= 22:11-22:40 / Total delay = 29 min
G.Soni
23 Sep 2026
Closed
bd-08-K2-2026-09-22
6
MSL/SID/MECH/K-03/08
07 Aug 2026
Sponge DRI
–
KILN -03 KILN GIRTH GEAR SPRING PLATE No-02, 03, 05&06 FORK CRACK. / TOTAL DELAY DURATION=16:48-17:48=60 MINUTE
Amit Singh
08 Aug 2026
Closed
bd-07-K3-2026-08-07
7
MSL/SID/MECH/K-01/33
24 Jul 2026
Sponge DRI
–
KILN -01 Kiln Girth Gear Slave Side Pinion shaft broken. / Delay time= 08:32-10:50 / Total delay = 138 min
L.K. Kaushik
25 Jul 2026
Closed
bd-06-K1-2026-07-24
8
MSL/SID/MECH/K-01/32
19 Jul 2026
Sponge DRI
–
KILN-01 BC-18 Conveyor Belt broken. / Delay time= 04:10-08:10 / Total delay = 240 min
Mr Amit Singh
21 Jul 2026
Closed
bd-05-K1-2026-07-19
9
MSL/SID/MECH/K-01/31
07 Jul 2026
Sponge DRI
–
KILN -01 Feed tube liner change due to avoid frequent jam. / Delay time= 00:00-00:23 / Total delay = 23 min
Mr D.k. Chandrakar
08 Jul 2026
Closed
bd-03-K1-2026-07-07
10
capa-2026-06-13-rca1
13 Jun 2026
Ferro Alloy
Furnace 1 Transformer
Furnace 1 Transformer B phase, B1 & B2 flexible short & spark
Electrical Ferro team
–
Closed
–
11
MSL/SID/MECH/K-01/30
30 Apr 2026
Sponge DRI
–
KILN -01 Kiln Girth Gear Master Side Pinion shaft broken. / Delay time= 12:43-21:00 / Total delay = 497 min
L.K. Kaushik
01 May 2026
Closed
bd-02-K1-2026-05-03
12
capa-2024-12-20-rca8
20 Dec 2024
Ferro Alloy
Furnace 4 Skip Hoist
Skip hoist no. 4 contactor stuck up during skip goes to upward direction
Vinod singh
–
Monitoring
–
13
capa-2024-12-20-rca7
20 Dec 2024
Ferro Alloy
Furnace 3
Furnace 3 Incommer 11 Kv Trip in Under voltage
Ajay kumar Soni
–
Monitoring
–